Monitoring and Control as Success Tools in Factory Construction: An Earned Value Analysis
DOI:
https://doi.org/10.67294/h5qg2t42Keywords:
Earned Value, Project Control, Industrial Construction, PMBOK, MozambiqueAbstract
Factory construction projects involve high investment, tight schedules, and multiple stakeholders, making monitoring and control decisive processes for project success. This paper analyses, through a practical case, the application of Earned Value Management (EVM) as an integrated schedule and cost control tool in the construction of an agro-industrial processing plant in northern Mozambique. The applied, quantitative study is grounded in a literature review and a single exploratory case study using simulated monthly Planned Value, Earned Value, and Actual Cost data, parameterized on documented deviation drivers (rainy-season productivity loss, delays in imported inputs, and price escalation) to protect site confidentiality. The data-collection instrument was a structured monthly project-monitoring record with explicit physical-progress rules (quantities completed and weighted milestones); the sample corresponds to six consecutive monthly reporting cycles (months 1 to 6) of a single agro-industrial processing-plant construction project in Ribaué, Nampula province, selected purposively as a case rather than drawn from a probabilistic population. Results show a mean Schedule Performance Index (SPI) of 0.88 (SD = 0.015) and a mean Cost Performance Index (CPI) of 0.91 (SD = 0.024) across the six months, with the CPI declining monotonically from 0.95 to 0.88 and crossing the critical 0.90 threshold in month five; by month six, SPI stood at 0.89 and CPI at 0.88, indicating simultaneous schedule slippage and cost overrun, with an estimate at completion (EAC) of about 13.66 million MZN, roughly 14% above the 12.0 million MZN budget (scenario range +7% to +21%). A work-package breakdown shows that earthworks and foundations concentrate half of the cost overrun, while steel structure and roofing concentrate 71% of the schedule slippage. The study concludes that EVM, framed within the PMBOK monitoring and controlling process group, enables early deviation detection and diagnosis and supports timely corrective decisions, confirming its relevance as a success tool in industrial construction; because the data are simulated, the results demonstrate the method rather than measure real performance.
References
Acebes, F., Pajares, J., Galán, J. M., & López-Paredes, A. (2014). A new approach for project control under uncertainty. Going back to the basics. International Journal of Project Management, 32(3), 423–434. https://doi.org/10.1016/j.ijproman.2013.08.003
Acebes, F., Pereda, M., Poza, D., Pajares, J., & Galán, J. M. (2015). Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques. International Journal of Project Management, 33(7), 1597–1609. https://doi.org/10.1016/j.ijproman.2015.06.012
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12–23. https://doi.org/10.1177/875697280303400403
Aramali, V., Sanboskani, H., Gibson Jr., G. E., El Asmar, M., & Cho, N. (2022). Forward-looking state-of-the-art review on earned value management systems: The disconnect between academia and industry. Journal of Management in Engineering, 38(3). https://doi.org/10.1061/(ASCE)ME.1943-5479.0001019
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Ayalew, G. G., & Ayalew, G. M. (2024). Developing fuzzy-based earned value analysis model for estimating the performance of construction projects: A case of selected public building projects in Ethiopia. Cogent Engineering, 11(1), 2348210. https://doi.org/10.1080/23311916.2024.2348210
Ayalew, G. M., Meharie, M. G., & Ayalew, G. G. (2023). Regression modeling for prediction of earned value indexes in public building construction projects: The case of Ethiopia. Cogent Engineering, 10(1), 2220497. https://doi.org/10.1080/23311916.2023.2220497
Barraza, G. A., Back, W. E., & Mata, F. (2004). Probabilistic forecasting of project performance using stochastic S curves. Journal of Construction Engineering and Management, 130(1), 25–32. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(25)
Batselier, J., & Vanhoucke, M. (2015a). Construction and evaluation framework for a real-life project database. International Journal of Project Management, 33(3), 697–710. https://doi.org/10.1016/j.ijproman.2014.09.004
Batselier, J., & Vanhoucke, M. (2015b). Evaluation of deterministic state-of-the-art forecasting approaches for project duration based on earned value management. International Journal of Project Management, 33(7), 1588–1596. https://doi.org/10.1016/j.ijproman.2015.04.003
Cândido, L. F., Carneiro, J. Q., & Heineck, L. F. M. (2016). Análise da aplicação da técnica de gerenciamento do valor agregado (EVM) em projetos de construção enxuta. Revista Produção Online, 16(3), 947–965. https://doi.org/10.14488/1676-1901.v16i3.2227
Ebekozien, A., Aigbavboa, C. O., & Ramotshela, M. (2024). A qualitative approach to investigate stakeholders' engagement in construction projects. Benchmarking: An International Journal, 31(3), 866–883. https://doi.org/10.1108/BIJ-11-2021-0663
Eisenhardt, K. M. (1989). Building theories from case study research. Academy of Management Review, 14(4), 532–550. https://doi.org/10.5465/amr.1989.4308385
El-Rayes, K., & Moselhi, O. (2001). Impact of rainfall on the productivity of highway construction. Journal of Construction Engineering and Management, 127(2), 125–131. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:2(125)
Flyvbjerg, B. (2006). Five misunderstandings about case-study research. Qualitative Inquiry, 12(2), 219–245. https://doi.org/10.1177/1077800405284363
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279–295. https://doi.org/10.1080/01944360208976273
Forquilha, S. (2015). Sector privado no contexto da implementação das reformas no sector agrário. Uma análise a partir de experiências locais. In Castel-Branco, C. N., Massingue, N. and Muianga, C. (orgs.), Questões sobre o desenvolvimento produtivo em Moçambique. Maputo: IESE.
Ibrahim, M. N., Thorpe, D., & Mahmood, M. N. (2019). Risk factors affecting the ability for earned value management to accurately assess the performance of infrastructure projects in Australia. Construction Innovation, 19(4), 550–569. https://doi.org/10.1108/CI-07-2018-0058
Ika, L. A. (2012). Project management for development in Africa: Why projects are failing and what can be done about it. Project Management Journal, 43(4), 27–41. https://doi.org/10.1002/pmj.21281
Ika, L. A., Diallo, A., & Thuillier, D. (2012). Critical success factors for World Bank projects: An empirical investigation. International Journal of Project Management, 30(1), 105–116. https://doi.org/10.1016/j.ijproman.2011.03.005
Kim, E., Wells, W. G., & Duffey, M. R. (2003). A model for effective implementation of earned value management methodology. International Journal of Project Management, 21(5), 375–382. https://doi.org/10.1016/S0263-7863(02)00049-9
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400–407. https://www.sciencedirect.com/science/article/pii/S0263786308000331
Medeiros, D. Z. B., Santana, M. G. C., Fernandes, J. L., & Fernandes, A. S. C. (2023). Aplicação de análise de valor agregado em um projeto de implementação de um negócio de produtos orgânicos. Revista Foco, 16(2), e1001. [URL/DOI to be confirmed by the authors]
Muriithi, N., & Crawford, L. (2003). Approaches to project management in Africa: Implications for international development projects. International Journal of Project Management, 21(5), 309–319. https://doi.org/10.1016/S0263-7863(02)00048-7
Nacala Corridor Agriculture Master Plan. (n.d.). Support of agriculture development master plan for Nacala Corridor in Mozambique: Interim report, Chapter 3 (Agriculture and climate of the Nacala Corridor). https://farmlandgrab.org/uploads/attachment/ITR(1)%20Chap-3-eng.pdf
Naeni, L. M., Shadrokh, S., & Salehipour, A. (2011). A fuzzy approach for the earned value management. International Journal of Project Management, 29(6), 764–772. https://doi.org/10.1016/j.ijproman.2010.07.012
Narbaev, T., & De Marco, A. (2014). An earned schedule-based regression model to improve cost estimate at completion. International Journal of Project Management, 32(6), 1007–1018. https://doi.org/10.1016/j.ijproman.2013.12.005
Navon, R., & Sacks, R. (2007). Assessing research issues in automated project performance control (APPC). Automation in Construction, 16(4), 474–484. https://doi.org/10.1016/j.autcon.2006.08.001
Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509–526. https://doi.org/10.1080/01446191003674519
Pajares, J., & López-Paredes, A. (2011). An extension of the EVM analysis for project monitoring: The cost control index and the schedule control index. International Journal of Project Management, 29(5), 615–621. https://doi.org/10.1016/j.ijproman.2010.04.005
Project Management Institute (PMI). (2021). A guide to the project management body of knowledge (PMBOK Guide) (7th ed.). Project Management Institute. https://www.pmi.org/standards/pmbok
Reda, S. G., Belachew, K. T., Demiss, B. A., & Ali, S. K. (2025). Performance evaluation of construction project by earned value management system in Amhara Waterworks Construction Enterprise. Discover Civil Engineering, 2, Article 25. https://doi.org/10.1007/s44290-025-00193-0
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007
Setiawan, M. H. I., Witjaksana, B., & Purnama, J. (2025). Analysis of project delays impact by cost in the construction of a light brick factory in Lamongan using the earned value method. International Journal of Mechanical, Industrial and Control Systems Engineering, 2(1), 1–8. https://doi.org/10.61132/ijmicse.v2i1.155
Thomas, H. R., & Sakarcan, A. S. (1994). Forecasting labor productivity using factor model. Journal of Construction Engineering and Management, 120(1), 228–239. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:1(228)
Turkan, Y., Bosché, F., Haas, C. T., & Haas, R. (2012). Automated progress tracking using 4D schedule and 3D sensing technologies. Automation in Construction, 22, 414–421. https://doi.org/10.1016/j.autcon.2011.10.003
U.S. Government Accountability Office (GAO). (2009). GAO cost estimating and assessment guide: Best practices for developing and managing capital program costs (GAO-09-3SP). https://www.gao.gov/products/gao-09-3sp
United Nations. (2015). Transforming our world: The 2030 Agenda for Sustainable Development (A/RES/70/1). https://sdgs.un.org/2030agenda
Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), 289–302. https://doi.org/10.1016/j.ijproman.2005.10.004
Vanhoucke, M. (2011). On the dynamic use of project performance and schedule risk information during project tracking. Omega, 39(4), 416–426. https://doi.org/10.1016/j.omega.2010.09.006
Willems, L. L., & Vanhoucke, M. (2015). Classification of articles and journals on project control and earned value management. International Journal of Project Management, 33(7), 1610–1634. https://doi.org/10.1016/j.ijproman.2015.06.003
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Sergio Vicente Gabriel, Chibalonza Mpenda (Author)

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.